  Multi Client Demobilisation & Mobilisation / Loading Weldex SL6000 Crawler Crane  Transport to Quay / Stored / Inspection / Loading Quay to Vessel x 64 Pieces (+ other equipment)  
 
  Project Specifications
   
  "Many thanks for safe and effecient discharging of our reels vessel to quay."

Dave Cruddis Work Center Leader Wellstream
 
 
 
Project :
Weldex - SL6000 - Load Crawler Crane 64 x Pieces

Workscope :
Unload Crawler Crane 64 x pieces transport to quay.   

Discharge 8 x Reels Empty 45T each Ex Wellstream

Load Crawler Crane 64 x pieces quay to vessel.

4 x Pieces National Oilwell Equipment (Drill  Line Reeler / Xmas Tree Holder)

Seafasten All equipment on board.

Location :
Under Radius of 250Ton SWL Dockside Crane – Shepherd Offshore - Offshore Technology Park – Walker - Newcastle

Shepherd Offshore Services Provided :
Transport Discharge / Storage / Post Load out Inspection /  Lifting Plan Review / Heavy & Abnormal lifting services / Seafastening Services / fast turnaround.
  Agent / Client:
Denholm Barwil / Wellstream /  Weldex

Vessel:
Jade C
145m Length / Draft 6m

Date / Time Arrival :
14/11/08 07:45hrs

Date / Time Departure :
16/11/08   14:10hrs

Dayshift
Diagrams
Click Image To Enlarge Diagram


       
Shepherd Offshore Comments:
We achieved a fast turn around for the vessel and managed to meet the individual targets for the various parties. Shepherd Offshore offloaded 8 x Empty Reels for Wellstream and removed them from radius of our dockside crane via straddle truck. Weldex Crawler Crane & Equipment was reviewed by all parties and then a loading sequence was agreed / confirmed with the vessel. We worked efficiently ensuring that the dockside crane was supplied continuously with equipment to load.