  Handling and logistics management of subsea trenching equipment for PFS and CTC Marine  
 
  Project Specifications
   
  "The cargo was a high-value sub-sea trenching unit. Shepherd Offshore carried out all services required, with some extra un-planned work at all times with a strong safety focus and attention to detail."

Andrew Wilson
Area Manager Pentagon Freight Services
 
 
 
Project :
UT 1

Workscope :
Loading Trencher x 1 to vessel & seafastening.

Location :
Hadrian Yard – Wallsend - Newcastle

Shepherd Offshore Services Provided :
Rigging Services / Tying Up & Releasing Vessel / Heavy & Abnormal Lifting Services / Fabrication & Seafastening Services.

  Agent / Client:
PFS / CTC

Vessel:
Ingeborg Pilot

Date :
Tuesday 18/3/08

12hrs shifts
Diagrams
Click Image To Enlarge Diagram


     
Shepherd Offshore Comments:
Working offsite at Wallsend we achieved a safe and efficient operation by understanding the objectives of all parties and listening to the various inputs then co-ordinating all parties with clear and direct lines of communication