Project Scope:
Groundwork’s; preparation and remediation of existing ship yard facility to create flat portside development area. Design, construction and commissioning of fully integrated manufacturing plant with access roads and outbound logistics routes..
Location:
Neptune Energy Park,
Newcastle-Upon-Tyne, UK
Shepherd Offshore Services Provided :
Shepherd Offshore provided a full turn-key solution from land remediation through final design, construction and logistics planning.
|
|
Project Specifications:
160m x 40m modular build specialist manufacturing factory complete with integrated offices, storage and utilities.
Timescales:
Facility completed in 10 months from initial planning through commissioning and handover.
Project Partners:
Elliott Associates
3e Consulting
Whelan Construction
Newcastle City Council
One North East |